CHORUS LINE

BERGAMO |

We were involved in a massive reclamation project in the former Ote area, where the new Chorus Life district is currently being built.

The contracted works included a displacement of 85,000.00 cubic metres at a depth of 11 metres from the pavement starting point, with low load-bearing and wet soil. Despe implemented a system that provided a safe working environment.

AREA: 2500.000 m² TIMEFRAME: 23 MONTHS IN TOTAL