Despe Logo
50 Years Badge
  • 关于我们
  • 领域
  • 项目
  • 联系方式
  • TDW

    拆除系統

  • SCK

    施工系統

  • 关于我们
  • 领域
  • 项目
  • 联系方式
  • TDW
  • SCK
菜單
关于我们
领域
项目
联系方式
TDW
SCK
社交InstagramFacebookYoutube
資訊Privacy PolicyCookie Policy
Whistleblowing

Despe s.p.a., in compliance with D.Lgs. 30 March 2023, n. 24 (c.d. Whistleblowing Decree) has established an internal reporting channel that allows you to report, in writing or orally, in strict confidentiality, violations of national or European Union regulatory provisions, of which the reporting agents have become aware within their working context inside the Company. The reports are addressed and managed by a subject inside the company, autonomous and specifically trained in the matter, in compliance with and in the protection of absolute confidentiality relating to the identity of the reporters and the content of the reports.

despe.whistlelink.com閱讀文件
Despe Logo
© 2025 DESPE S.p.a. società unipersonale Società soggetta all'attività di direzione e coordinamento di Felicità S.r.l P. IVA 00478770167

Via Leonardo da Vinci, 12/14
24060 Torre de’ Roveri (BG)

P. IVA 00478770167
Tel: +39 035 4218100

Site by BARR

Endesa热电站

烟囱
Tavazzano
烟囱
Tavazzano

我们面临的挑战是要拆除高250米的烟囱,其高度令人难以置信。我们采用了本公司设计的专用液压平台 ’Red O-Ring’以保证施工的安全性。施工时将该项智能设备安装到烟囱顶部,随着逐渐拆除烟囱,液压平台不断下降,拆除时所有废料及粉尘均落在保护环内部。

项目编号

底座直径

24米

顶径

12米

壁厚

25〜110厘米

耗时

9个月