Despe Logo
50 Years Badge
  • About us
  • Sectors
  • Projects
  • Contacts
  • TDW

    Demolition System

  • SCK

    costruction System

  • About us
  • Sectors
  • Projects
  • Contacts
  • TDW
  • SCK
Menu
About us
Sectors
Projects
Contacts
TDW
SCK
SocialInstagramFacebookYoutube
InfoPrivacy PolicyCookie Policy
Whistleblowing

Despe s.p.a., in compliance with D.Lgs. 30 March 2023, n. 24 (c.d. Whistleblowing Decree) has established an internal reporting channel that allows you to report, in writing or orally, in strict confidentiality, violations of national or European Union regulatory provisions, of which the reporting agents have become aware within their working context inside the Company. The reports are addressed and managed by a subject inside the company, autonomous and specifically trained in the matter, in compliance with and in the protection of absolute confidentiality relating to the identity of the reporters and the content of the reports.

despe.whistlelink.comRead document
Despe Logo
© 2025 DESPE S.p.a. società unipersonale Società soggetta all'attività di direzione e coordinamento di Felicità S.r.l P. IVA 00478770167

Via Leonardo da Vinci, 12/14
24060 Torre de’ Roveri (BG)

P. IVA 00478770167
Tel: +39 035 4218100

Site by BARR

Endesa power station

Chimney Stack
Tavazzano
Chimney Stack
Tavazzano

The challenge was to demolish a chimney stack with an incredible height of 250 metres. To do so in completely safe conditions, we used the special hydraulic platform 'Red o-Ring' that we designed in-house. An intelligent tool that is mounted on the top of the chimney and descends step-by-step, as the demolition proceeds, retaining all that the demolition work produces within itself. The chimney keeps everything inside, dust included.

project numbers

BASE DIAMETER

24 M

TOP DIAMETER

12 M

WALL THICKNESS

FROM 25 TO 110 CM

TIMING

9 MONTHS